In a September 2025 announcement, Henan Mine Crane reported that a double-hook lifting-beam gantry crane it built for a Baosteel Zhanjiang project had passed A inspection. The company reported that manufacturing had finished two months ahead of the original plan, bringing the equipment to delivery readiness.

The company says the crane uses PLC and variable-frequency control, a safety-monitoring system and CMS condition monitoring. Interfaces are reserved for a future unmanned-operation upgrade.
A two-day acceptance program involved specialists from the Zhanjiang project, Ouyeel Industrial Products, Dalian Baoxin and Shanghai Jinyi Testing. They reviewed self-inspection, material and nondestructive-testing records and carried out powered tests of hoisting, travel and electrical systems.
The company credited coordination with Ouyeel on components and quality control, together with a joint production team involving model worker Li Jie and major-project specialists.